wrgodsend
Electrical
- Jul 3, 2006
- 1
I own a custom home theater company and I'm trying to organize our projects through a work breakdown structure. Anyway, I'm having problems with the finish date. I enter in the work hours in the "Work" column as well as the duration in "duration" column. However, when I enter in the duration, for example 1 day, the start date will reflect 7/17 which is correct but the finish date reflects 7/18. Because the task duration is 1 day, I want the finish date to show 7/17 not 7/18. The finish date is making my project end 1 day later than it's supposed to.
This is my first WBS I've done on Project and I can't seem to find any answers for my question. Thank you so much, any advice is greatly appreciated.
This is my first WBS I've done on Project and I can't seem to find any answers for my question. Thank you so much, any advice is greatly appreciated.