Coast2Coast
Civil/Environmental
- Apr 1, 2024
- 4
I have a client who needs an "after the fact structure" foundation adequacy letter. I've done as-built letters for contractors that had receipts and pictures to verify, but this one - it was constructed a decade ago by the previous owner. It's just a pole building, with posts about a 3 ft embedment (so he says) into our clayey soil.
What is the strategy to prove this? Do we need to dig down beside the posts? The have a 3-4" layer of concrete poured around them.
Suggestions?
What is the strategy to prove this? Do we need to dig down beside the posts? The have a 3-4" layer of concrete poured around them.
Suggestions?