jcfowler79
Civil/Environmental
- May 11, 2004
- 5
Working on a project near a small municipal airport. FAA requires that dry bottom ponds be empty 48 hours after the storm event has concluded. City requires 2-year and 100-year restriction for the 24-hour event necessitating a dual stage restrictor. For the life of me I can not get the pond to drain down in 48 hours if the 2-year restriction meets the requirement. In this case 0.04 cfs/trib acre. The orifice is just too small to allow the water to drain out quickly enough. We can not have open water without bird - balls, netting etc so open water is out of the question. I need dry bottom that drains in 48 hours and meets a 2-year discharge rate, is it even possible? I have changed orifice shape from a circle to rectangle to maximize flow area at lower depths and still no progress. Any one have experience or documentation of a municipality waiving certain requirements near an airport?