I'm currently designing a multi-span (4 bays at 62') PT beam and am trying to reconsile the seismic design between RAM Concrete and ADAPT-PT. I'm trying to decide/calculate the amount of PT to utilize in the lateral force resisting system. The PTI Manual makes a reference to using , 0% or 25% to 65% for pre-stressing, but I'm unable to find a "hard-and-fast" reference as to the amount of PT to use in the ADAPT post-processor calculations.
Any insight would be helpful.
Mike
Any insight would be helpful.
Mike