ohms
Electrical
- Jul 24, 2004
- 17
Hi every one,
In our substation, the route of the HV power cable is through trench and pipe ducts. Pipe ducts consititute 25% of the route.
For Cable calculations, how should we consider the laying method of the cable. Trench, Pipe duct or the worst of both.
Or we do the calculation separately for Trench part and separately for pipe duct route and take into consideration the worst case.
What IEC recommends in such scenario.
Thanks for you time,
Ohms
In our substation, the route of the HV power cable is through trench and pipe ducts. Pipe ducts consititute 25% of the route.
For Cable calculations, how should we consider the laying method of the cable. Trench, Pipe duct or the worst of both.
Or we do the calculation separately for Trench part and separately for pipe duct route and take into consideration the worst case.
What IEC recommends in such scenario.
Thanks for you time,
Ohms