bbqq021
Petroleum
- Feb 26, 2012
- 5
We are due to complete an offshore lift of approximately 370 tonnes in about 2 months. The structure is a mid-water-arch which will support 2 risers for an FSO in the gulf of Thailand. Our installation contractor has specified the dynamic factors which considers the motion of the floating vessel and the added mass as the structure is lowered through the surface and then through the water column, long story short we have come up with a beam of 600 tonnes SWL. The design of the beam will follow B30.20 as well as the supplement ASME BTH-1 for design. The beam will only be used once.
According to BTH-1 the Design category of this beam is “B” (environmental loads are not easily predictable) and so the design factor is 3.00 compared to 1.67 from AISC or 2 for Cat A. This is all fine and understood.
My problem is that the company I work for mandates that all portable lifting equipment should be proof loaded according to BTH and OSHA (125%). This is not practical and in the past when we have had large lifting equipment we have used NDT and the design of the beam to demonstrate integrity and compliance. The problem is BTH has very weak language like “should be load tested to 125%”. I know NDT and design is a common practice when it comes to large lifts however I cannot cite a code or practice. Can anybody point me in the right direction?
My second question is what kind of NDT? I guess the answer to the first question may include an answer to this however at the very least I was thinking 100% RT where possible and 100% UT for other primary structure.
Thanks for your help in advance.
Will
According to BTH-1 the Design category of this beam is “B” (environmental loads are not easily predictable) and so the design factor is 3.00 compared to 1.67 from AISC or 2 for Cat A. This is all fine and understood.
My problem is that the company I work for mandates that all portable lifting equipment should be proof loaded according to BTH and OSHA (125%). This is not practical and in the past when we have had large lifting equipment we have used NDT and the design of the beam to demonstrate integrity and compliance. The problem is BTH has very weak language like “should be load tested to 125%”. I know NDT and design is a common practice when it comes to large lifts however I cannot cite a code or practice. Can anybody point me in the right direction?
My second question is what kind of NDT? I guess the answer to the first question may include an answer to this however at the very least I was thinking 100% RT where possible and 100% UT for other primary structure.
Thanks for your help in advance.
Will