I am told that the relief calc in sect VIII changed in 1978. I have been asked to investigate this due to that fact that a safety on a boiler steam drum needs to be replace in the furture. The vendor's quote for an identical replacement valve at the original design inlet conditions now has an increase in the outlet capacity of ~20%.
I am looking to understand the details of the change in calc. The code of the day was 1970 and I do not have access to a copy of this code. Any and all help would be greatly appreciated.
Also, does anyone have experience with this situation.
Thanks!
I am looking to understand the details of the change in calc. The code of the day was 1970 and I do not have access to a copy of this code. Any and all help would be greatly appreciated.
Also, does anyone have experience with this situation.
Thanks!