Hi guys,
I am a structural engineer who is doing a structural design of precast driven piles for a bridge abutment. I have run down the loads and the geotech report makes the follow suggestions.
1. Because the piles are driven to refusal, the capacity of the pile will be governed by the structural capacity.
2. Undersized pre-boring will be required to facilitate driving through a stiff stratum of bedrock.
My questions are:
If my piles are 500 diameter, what diameter should I make the pre-bore and what should I be looking out for? All help will be greatly appreciated.
I am a structural engineer who is doing a structural design of precast driven piles for a bridge abutment. I have run down the loads and the geotech report makes the follow suggestions.
1. Because the piles are driven to refusal, the capacity of the pile will be governed by the structural capacity.
2. Undersized pre-boring will be required to facilitate driving through a stiff stratum of bedrock.
My questions are:
If my piles are 500 diameter, what diameter should I make the pre-bore and what should I be looking out for? All help will be greatly appreciated.