What are your thoughts for not connecting a precast concrete pile to the pile cap when the loads are gravity only. I'm working on a design/build project and the contractor want's to save money by eliminating the epoxy anchors typically required to connect the two systems. I currently show the detail with a 6" embedment and no rebar to connect the two. I'm in a high seismic zone so I'm a little concerned about the lateral.