Could anyone shed some lights on the 16 foot long precast lintel I plan to use for a non-load-bearing interior masonry wall?
1. Does the precast lintel somehow need to be positively connected to the CMU at jamb, with dowels? If so, how?
2. Does the rebar in the CMU wall sitting on the lintel need to be doweled/drilled into this precast lintel, or if grout would be sufficient to hold them together?
3. Whose responsibility is it for the design of this precast lintel? Should EOR call out and detail the reinforcing in the precast, or should it be precaster' responsibility?
Thank you.
1. Does the precast lintel somehow need to be positively connected to the CMU at jamb, with dowels? If so, how?
2. Does the rebar in the CMU wall sitting on the lintel need to be doweled/drilled into this precast lintel, or if grout would be sufficient to hold them together?
3. Whose responsibility is it for the design of this precast lintel? Should EOR call out and detail the reinforcing in the precast, or should it be precaster' responsibility?
Thank you.