slange
Civil/Environmental
- Aug 15, 2017
- 9
I need to preliminary size a ditch to contain the floodplain and floodway. I used Chezy Mannings to calculate, and it calculated a Q well over what my hydrology calculated. I then placed in the Hec Ras model and it over tops the ditch, roadway, etc. I know that the downstream structure will create a tailwater condition but not sure why the ditch doesn't contain the water. I did a 6' deep trapezoidal channel with 3:1 side slopes and 75' wide. My Hydrology states that there is 1228 cfs being directed to the channel.
Chezy Mannings assumptions
Depth of ditch 5' (want about a foot of freeboard)
ditch bottom width: 75'
sideslopes: 3:1
n: .025 Natural channel
S: .004 Ft/Ft
A: 2(5*15/2)+5*75= 450sqft
R: A/P P=(sqrt(5^2+15^2))2+75=106.62 R=450/106.62=4.22
Q=1.49/.025*(450)*(4.22)^.67*(.004)^.5= 4450.9 cfs
so the ditch should be able to handle 4451 cfs correct or am I doing something wrong. I appreciate any help.
Chezy Mannings assumptions
Depth of ditch 5' (want about a foot of freeboard)
ditch bottom width: 75'
sideslopes: 3:1
n: .025 Natural channel
S: .004 Ft/Ft
A: 2(5*15/2)+5*75= 450sqft
R: A/P P=(sqrt(5^2+15^2))2+75=106.62 R=450/106.62=4.22
Q=1.49/.025*(450)*(4.22)^.67*(.004)^.5= 4450.9 cfs
so the ditch should be able to handle 4451 cfs correct or am I doing something wrong. I appreciate any help.