Muhammad Ijaz
Mechanical
- Apr 8, 2005
- 30
Dear Sir,
1" NPT threaded carbon steel elbows (3000#) and piping are installed at downstream of control valve drain. Service is hot compressed air (P = 7.5 bar and Temp = 350 deg C).
Control valve is passing.
Now it is required to install NPT valve at open end (drain end) of piping to contain compressed air. it will result in increase in pressure at outlet piping and threaded connections may leak.
Please let me know calculation procedure for NPT threads against pressure and leakage.
Regards,
Ijaz
1" NPT threaded carbon steel elbows (3000#) and piping are installed at downstream of control valve drain. Service is hot compressed air (P = 7.5 bar and Temp = 350 deg C).
Control valve is passing.
Now it is required to install NPT valve at open end (drain end) of piping to contain compressed air. it will result in increase in pressure at outlet piping and threaded connections may leak.
Please let me know calculation procedure for NPT threads against pressure and leakage.
Regards,
Ijaz