HnAw
Mining
- Sep 10, 2013
- 3
i have main line in a decline 1700 meters lenght, with 270 meters head until end of main, it has hose cabinet each 40 meters lng, i'm putting pressure regulating valve but im not changing rating valves 175 lb nor flanges 150#, due i'm using PRV,is necessary change to 300# rating?