ssr49119
Chemical
- Apr 1, 2015
- 2
We are working on a existing crude oil pipeline which has an existing pressure reduction skid & destination is ship. A new tap off from this existing pipeline downstream of the existing pressure reduction skid goes to a storage tank farm. A new PCV is shown on this tap off for controlling the pressure of crude oil going to the inlet of the floating roof storage tanks. Flow rate varies from 3333 barrels/hr to 9375 barrel/hr. Pressure at inlet of existing pressure reduction skid varies from 800 psig to 1400 psig depending on the flow rate. Distance between existing pressure reduction skid and new PCV is around 800 metres. Will this system of having a PCV downstream of existing pressure reduction skid work properly or will the new PCV and existing pressure reduction skid fight with each other? Awaiting your esteemed response to this query.