TiCl4
Chemical
- May 1, 2019
- 615
Background
I need to add some NPS 2" nozzle to the top heads of several Section VIII Div 1 pressure vessels. The vessels are older (1960s/70s) and have undergone a fitness-for-service (FFS) evaluation that de-rated them (from 50/75 psig down to 25-35 psig) due to a few thinner nozzles that did not have reinforcement pads. The shells and heads have shown no corrosion over the years from original design based on most recent thickness tests a few years ago.
During the FFS evaluation, I noticed that all nozzles 2" and under were excluded from consideration in the COMPRESS calculations. I need to add some new nozzles, and want to check with the good members of this forum to ensure I am going about this the right way.
As far as I can find it, ASME VII Div 1, UG-36 (c)(3) states that reinforcement is not need for welded connections provided:
(-a)(-1) 3.5 in diameter - in vessel shells or heads with a required minimum thickness of 3/8 in. or less
(-a)(-2) 2-3/8 in diamter - in vessel shells or heads over a required minimum thickness of 3/8 in.
The vessels are a mix of 7/16" and 3/16". The FFS report has two "required" thickness stated:
[ol 1]
[li]Minimum thickness per UG-16: In all cases the required thickness is 0.0625", well less than 3/8".[/li]
[li]Design thickness due to internal pressure (t): Ranges from 0.15-0.2", but still less than 3/8".[/li]
[/ol]
My main question(s)
Am I right in my thinking that adding these NPS 2" nozzles are covered by UG-36(c)(3) and will not need any calculations to ensure MAWP remains unchanged? I will be sure to follow the spacing provision in UG-36 that limit the proximity of multiple non-reinforced openings.
If I am correct in the above assumption, is there anything I need to do other than normal NDT post-weld and inspector sign-off to add these nozzles? My location does not require ASME VIII as law, and there is no state pressure vessel inspector that must be consulted. Despite that, I have started requiring the site to have repairs "R"-stamped, and all modifications must follow code.
Am I missing anything?
I need to add some NPS 2" nozzle to the top heads of several Section VIII Div 1 pressure vessels. The vessels are older (1960s/70s) and have undergone a fitness-for-service (FFS) evaluation that de-rated them (from 50/75 psig down to 25-35 psig) due to a few thinner nozzles that did not have reinforcement pads. The shells and heads have shown no corrosion over the years from original design based on most recent thickness tests a few years ago.
During the FFS evaluation, I noticed that all nozzles 2" and under were excluded from consideration in the COMPRESS calculations. I need to add some new nozzles, and want to check with the good members of this forum to ensure I am going about this the right way.
As far as I can find it, ASME VII Div 1, UG-36 (c)(3) states that reinforcement is not need for welded connections provided:
(-a)(-1) 3.5 in diameter - in vessel shells or heads with a required minimum thickness of 3/8 in. or less
(-a)(-2) 2-3/8 in diamter - in vessel shells or heads over a required minimum thickness of 3/8 in.
The vessels are a mix of 7/16" and 3/16". The FFS report has two "required" thickness stated:
[ol 1]
[li]Minimum thickness per UG-16: In all cases the required thickness is 0.0625", well less than 3/8".[/li]
[li]Design thickness due to internal pressure (t): Ranges from 0.15-0.2", but still less than 3/8".[/li]
[/ol]
My main question(s)
Am I right in my thinking that adding these NPS 2" nozzles are covered by UG-36(c)(3) and will not need any calculations to ensure MAWP remains unchanged? I will be sure to follow the spacing provision in UG-36 that limit the proximity of multiple non-reinforced openings.
If I am correct in the above assumption, is there anything I need to do other than normal NDT post-weld and inspector sign-off to add these nozzles? My location does not require ASME VIII as law, and there is no state pressure vessel inspector that must be consulted. Despite that, I have started requiring the site to have repairs "R"-stamped, and all modifications must follow code.
Am I missing anything?