I would like to know if it is acceptable for a pressure vessel, designed and built according to ASME VIII div 1 to be directly welded to the incoming & outgoing piping instead of flanged connection. I am discussing with a contractor who suggets to weld the piping directly to the vessel nozzles. The system is designed for power piping carrying steam at around 90psig - piping design is to B31.1. Comments appreciated. Thanks