How would you go about estimating the production on the installation of a 12" C900 DR-14 PVC Water Main installed in rural Nebraska? 5' cover. 2 crews each consisting of 1 backhoe operator and 2 pipe fitters. I have 14,500 feet to install. No groundwater, little to no utilities.