New to Project here. Why do some of my Resource names show a % value such as John Smith [200%]? What exaclty is that info, and is there a toggle for that display?
Thanks for the info. I'm curious as to why this particular resource shows in gantt view as [200%], however, when I look in resource usage view, he is assigned 1 day of work, with 20% allocation. His name also for some reason shows as red in this view.
% are what we call 'unit', in your case, it means that you guy is planned to work 200% of his time. Check his allocation by going to view, resources sheet and search for the red allocations, and reduce them !!