glubad55
Mechanical
- Nov 8, 2012
- 5
I frequently have issues with MS Project 2010 adding phantom time into my tasks, as shown in my attached photo.
My task calendar is 24 hours (no holidays or time off), task type is Fixed Work, task constraint is As Soon As Possible, and the affected tasks match up nicely on the calendar with the other tasks.
See the line in italics. It starts on Wednesday at 2 pm with a 2-hr duration. Given that I have specified (read: "made sure that it has") 2 hours of work, it should calculate easily. Instead, it adds something like 2.5 days to the project.
Note: I can drag the task "bar" located the right sidei n the Gantt Chart to the left and that generally fixes it, but without scouring the entire project for this, I might be unnecessarily adding precious hours to a project, and in a very large project where this random addition occurs, this could become an engineer's nightmare.
My task calendar is 24 hours (no holidays or time off), task type is Fixed Work, task constraint is As Soon As Possible, and the affected tasks match up nicely on the calendar with the other tasks.
See the line in italics. It starts on Wednesday at 2 pm with a 2-hr duration. Given that I have specified (read: "made sure that it has") 2 hours of work, it should calculate easily. Instead, it adds something like 2.5 days to the project.
Note: I can drag the task "bar" located the right sidei n the Gantt Chart to the left and that generally fixes it, but without scouring the entire project for this, I might be unnecessarily adding precious hours to a project, and in a very large project where this random addition occurs, this could become an engineer's nightmare.