MM904
Aerospace
- Apr 4, 2019
- 16
Hi all,
I have postedI am working on a rocket engine that will use HTP (98% concentrated hydrogen peroxide) as an oxidizer. Right now I am designing the hot fire testing tanks. Peroxides are awfully hard to work with because they continuously decompose, but I've found resources to get me along: Papers regarding storage of H202 (generally long-term, not pressurized) and typical ASME boiler standards for pressure vessel sizing, but most all of the ASME stuff have some form of "Not applicable for storage of H202, see reference X" which just brings me back to the first type of papers.
Even so, the design is 90% done. For reference, the tank specs are roughly as follows:
Capacity ~ 200 gallons
Max operating pressure: About 14 MPa
Material: 316 SS
Dimensions: Cylindrical shape, roughly 4 feet in diameter and 3 feet tall, with a wall thickness of about ~2 inches.
Storage duration: Less than a week.
Pressurized storage duration: Less than a day.
The last issue is sizing the pressure relief valve and the burst disc, which is giving me all sorts of issues as the two types of resources I've found have zero overlap on this part. I will need the tanks to be manufactured to the ASME code, however the manufacturers I've spoken with won't touch the sizing of the PRV and burst disc, they have asked me to provide that info for them, then they'll make me the tank. Any pointers or tips on how I can size these components correctly considering I'm holding HTP at high pressures would be much appreciated!
P.S. I am not opposed to simply oversizing the hell out of everything and calling it a day. However, to oversize something, you must first size that thing.
I have postedI am working on a rocket engine that will use HTP (98% concentrated hydrogen peroxide) as an oxidizer. Right now I am designing the hot fire testing tanks. Peroxides are awfully hard to work with because they continuously decompose, but I've found resources to get me along: Papers regarding storage of H202 (generally long-term, not pressurized) and typical ASME boiler standards for pressure vessel sizing, but most all of the ASME stuff have some form of "Not applicable for storage of H202, see reference X" which just brings me back to the first type of papers.
Even so, the design is 90% done. For reference, the tank specs are roughly as follows:
Capacity ~ 200 gallons
Max operating pressure: About 14 MPa
Material: 316 SS
Dimensions: Cylindrical shape, roughly 4 feet in diameter and 3 feet tall, with a wall thickness of about ~2 inches.
Storage duration: Less than a week.
Pressurized storage duration: Less than a day.
The last issue is sizing the pressure relief valve and the burst disc, which is giving me all sorts of issues as the two types of resources I've found have zero overlap on this part. I will need the tanks to be manufactured to the ASME code, however the manufacturers I've spoken with won't touch the sizing of the PRV and burst disc, they have asked me to provide that info for them, then they'll make me the tank. Any pointers or tips on how I can size these components correctly considering I'm holding HTP at high pressures would be much appreciated!
P.S. I am not opposed to simply oversizing the hell out of everything and calling it a day. However, to oversize something, you must first size that thing.