Canadaian
Geotechnical
- Feb 16, 2006
- 13
Hi
As all you may know it is possible to encounter near surface obstruction during installation of Prefabricated Vertical Drains PVD ... I understand that pre augering ( or other method may be chosen by the Contractor) is used to clear the obstruction for a certain depth to facilitate the PVD installation.
For this project PVD is to be used for the first time in the project area and to mitigate risk and unjustified high bidding rate, the client proposed that obstruction clearance shall be a separated item from the PVD installation. The question: is there any criteria or method to be followed to make sure that the Contractor do not abuse the item (do preaugering unnecessarily) I am thinking about power criteria. I know that in one project there was a load cell installed in some way to the PVD reel and there was a limit to define refusal, but it seems to me so dedicated and" sophisticated". Is the PVD rig equipped with some device that can tell us the operator had used the maximum machine power, so we can switch to obstruction clearance technique?
Thanks in Advance.
kiki
As all you may know it is possible to encounter near surface obstruction during installation of Prefabricated Vertical Drains PVD ... I understand that pre augering ( or other method may be chosen by the Contractor) is used to clear the obstruction for a certain depth to facilitate the PVD installation.
For this project PVD is to be used for the first time in the project area and to mitigate risk and unjustified high bidding rate, the client proposed that obstruction clearance shall be a separated item from the PVD installation. The question: is there any criteria or method to be followed to make sure that the Contractor do not abuse the item (do preaugering unnecessarily) I am thinking about power criteria. I know that in one project there was a load cell installed in some way to the PVD reel and there was a limit to define refusal, but it seems to me so dedicated and" sophisticated". Is the PVD rig equipped with some device that can tell us the operator had used the maximum machine power, so we can switch to obstruction clearance technique?
Thanks in Advance.
kiki