katty11
Petroleum
- May 6, 2008
- 16
Good mornign all, question...we are trying to change the service of existing equipment to a high H2s service which wil require us to PWHT the SA516-70 material. the original data sheet and service did not require PWHT. what should i be preprared for? I understand we will have to be NBIC compliant,