TOMMY2010
Structural
- Nov 1, 2020
- 18
Dear Members,
Hope you are all well!
I am facing a situation where we already have done welding of two joints (φ24" | thickness of 18mm | Material. A387 Gr11 Cl2) which is a in process piping job according to B31.3.
What happened that one of my colleges already did all checks during welding according to our WPS.
Fit-Up--> Preheating --> Welding --> In the last step for this alloy material he was supposed to go with PWHT after welding but he didn't as our client told him verbally not to go with PWHT till he makes volumetric NDT with UT before PWHT. Also, The line has a refractory lining and it will complicated to run through cutting and rewelding.
For some technical issues, The NDT team which will proceed for the job came after 3 days of the welding finished. and now the client is complaining for the long time ( More than 1 day they said without mentioning a reference for that speaking ) it takes before the NDT team did the inspection and they wanted those joints to be cut !!
1. Is our client right for that and is there any reference for his speech ?
2. Is it actually a problem or not and
3.Is there any reference that might help in making a good decision in this situation?
Appreciating your time and help,
Thanks and regards.
Hope you are all well!
I am facing a situation where we already have done welding of two joints (φ24" | thickness of 18mm | Material. A387 Gr11 Cl2) which is a in process piping job according to B31.3.
What happened that one of my colleges already did all checks during welding according to our WPS.
Fit-Up--> Preheating --> Welding --> In the last step for this alloy material he was supposed to go with PWHT after welding but he didn't as our client told him verbally not to go with PWHT till he makes volumetric NDT with UT before PWHT. Also, The line has a refractory lining and it will complicated to run through cutting and rewelding.
For some technical issues, The NDT team which will proceed for the job came after 3 days of the welding finished. and now the client is complaining for the long time ( More than 1 day they said without mentioning a reference for that speaking ) it takes before the NDT team did the inspection and they wanted those joints to be cut !!
1. Is our client right for that and is there any reference for his speech ?
2. Is it actually a problem or not and
3.Is there any reference that might help in making a good decision in this situation?
Appreciating your time and help,
Thanks and regards.