Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

PWHT for nonpressure parts to pressure parts - ASME Sec VIII Div I (2023)

Status
Not open for further replies.

Vessel-SA

Mechanical
Jun 7, 2022
8
Hi everyone,

I am trying to figure out whether PWHT (Post Weld Heat Treatment) is required per code for non-pressure parts welded to pressure parts under the following conditions:

The material is P1 Gr.1 for both the pressure part and non-pressure parts. PWHT is not required for service.

1) The thickness of the pressure part is 1.75". The non-pressure part (clip) is 1" thick. The fillet throat thickness is 0.75".

2) The thickness of the pressure part is 1.75". The non-pressure part (clip) is 1.625" thick. The fillet throat thickness is 0.5".

I am confused because UW-40(f)(5) states "the thickness of the weld at the point of attachment when a non-pressure part is welded to a pressure part" is the nominal thickness as used in table UCS-56-1. My understanding is that PWHT is not required for either (1) or (2) because the weld thickness is not greater than 1.5".
On the other hand, note (b)(3)(c) to table UCS-56-1 states PWHT is not mandatory "for fillet welds with a throat thickness of 1/2 in. (13 mm) or less used for attaching non-pressure parts to pressure parts. When the thickness of the pressure part exceeds 1 1/4 in. (32 mm), preheat to a minimum temperature of 200°F (95°C) shall be applied prior to welding each pass". This tells me the weld in example (1) requires PWHT but the weld in example 2 is exempt from PWHT.

Thanks!

 
Replies continue below

Recommended for you

What I mean is, scenario 1 requires PWHT and Scenario 2 does not, if pre-heated.
 
Thank you for your reply but what about the UW-40(f)(5)(-f) that states the nominal thickness is the thickness of the weld at the point of attachment when a non-pressure part is welded to a pressure part? The weld thickness in (1) is 0.75" and it is less than 1.5" which requires PWHT (if preheat) per table UCS-56-1 note (b)(2).
 
Assuming minimum preheat, neither weld requires PWHT by code
 
Your second question made me actually open the Code.....you missed quoting an important part of the note in Table UCS-56. Note (b)(3) is exemptions to mandatory PWHT due to service (U-2)...and therefore not applicable to this scenario.
 
@ Krausen
the preaheat is required if the nominal thickness (weld thickness) is greater than 1.25", isn't it correct? so why would you think it is required?
 
@david339933
No, I didn't miss that part. I didn't post that part simply because those exemptions are applicable whether or not the PWHT is due to service or another part of the code. I base this off of an ASME interpretation below (question 3). Although the interpretation is too old, and I am not sure if it is applicable to the recent editions.
Standard Designation:

BPV Section VIII Div 1
Edition/Addenda:
Para./Fig./Table No:
Subject Description:
Section VIII, Division 1, UCS-56
Date Issued: 04/11/1978
Record Number: BC-77-790
Interpretation Number : VIII-78-43

Question(s) and Reply(ies):

Question (1): Is it the intent of UCS-56(d)(6) and Note (2)(a) to Table UCS-56 that the exemption from postweld heat for material 1-1/2 in. and less, provided preheat over 1-1/4 in. is employed, applies to the thickness of the weld attaching a nonpressure part to a pressure part?

Reply (1): No. The reference to 1-1/2 in. as described in the above question applies to the thickness of the pressure part and not to the thickness of the weld. The provisions of UCS-56(d)(6) which refer to the thickness of the weld at the point of attachment when a nonpressure part is welded to a pressure part are applicable to the minimum time at normal temperature for nominal thickness if the weld requires postweld heat treatment.

Question (2): Which of the following statements regarding fillet weld size and exemption from postweld heat treatment where nonpressure parts are attached to pressure parts is correct?
(a) Fillet welds with a throat greater than 1/2 in. require postweld heat treatment when the thickness of the pressure part exceeds 1-1/4 in. and preheat is not used.
(b) Fillet welds with a throat less than 1/2 in. need not be postweld heat treated if preheat is used when the pressure part exceeds 1-1/4 in.
(c) Fillet welds with a throat less than 1/2 in. need not be postweld heat treated regardless of the thickness of the pressure part or the fact that preheat is not applied.

Reply (2): Items (a) and (b) are correct statements. Item (c) is incorrect.

Question (3): Do the exemptions in Notes (3)(a), (b), and (c) apply only if postweld heat treatment is required by UW-2?

Reply (3): No. The exemption in these Notes apply in any instance where a mandatory heat treatment was required.
 
@Krausen, david339933. could you tell me what you think of what I said?

I would appreciate it if anyone else could chime in too
 
The PWHT requirements are typically defined by the materials and joints in/of the pressure envelope.
If your vessel does not require PWHT as per the Core rules - so your non pressure attachments wouldn't need it too.
If you're trying to determine whether you need PWHT based on the fillet weld sizes of your non-pressure attachment to your pressure envelope - I would say you're doing something wrong with the design.

By the way - your first weld combo isn't possible. 19.05 mm throat makes for 27 mm long fillet:
You can't allocate 27 mm fillet on a 25.4mm thick detail.

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor