Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

PWHT Requirements As Per UCS-56-1 General Notes b (1) & (2) 1

Status
Not open for further replies.

SmallInfo

Petroleum
Oct 30, 2017
104
Hi Experts
I'm a bit confused about the differences between these highlighted points. Can you please help me understand them better?
Thanks in Advance
DIFFERENCE_g0m0z7.png
 
Replies continue below

Recommended for you

If the nominal thickness exceeds 1-1/4" you must preheat your welds, or else you have to do PWHT.

If the nominal thickness exceeds 1-1/2" you must ALWAYS do PWHT.
 
This is one of those rare cases where the Code language reads exactly as it means :)

Regards,

Mike

The problem with sloppy work is that the supply FAR EXCEEDS the demand
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor