Blizzardo
Industrial
- Jan 6, 2016
- 15
I have a question related to a Section VIII Div 1 U-stamped vessel. The vessel is manufactured of SA516 Grade 70 (P1) - 2.5" wall thickness, running at 150 PSI and 350F. We need to add-in a number of nozzles to the vessel. The nozzles are SA789 (P10H) and SA240 (P10H) respectively. Where the nozzles are to be cut in, it is expected that the welding work is to be completed with 309L stainless filler metal. In consideration of both ASME Section VIII and NBIC Section 3, is Post Weld Heat Treatment (PWHT) of the nozzle locations an absolute, or can this be eliminated?
Further to the above, there are some attachments on the interior of the vessel (SA240 - average thickness 1/2" - 3/4") that will require welding to the interior of the vessel (fillet welds). The filler metal is expected to be 309L stainless. Would PWHT be an absolute requirement at the weld locations (P1 to P8)?
Any assistance is greatly appreciated.
Further to the above, there are some attachments on the interior of the vessel (SA240 - average thickness 1/2" - 3/4") that will require welding to the interior of the vessel (fillet welds). The filler metal is expected to be 309L stainless. Would PWHT be an absolute requirement at the weld locations (P1 to P8)?
Any assistance is greatly appreciated.