Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations MintJulep on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

PWHT

Status
Not open for further replies.

cacacho

Mechanical
Dec 29, 2010
6
IS A REINFORCED,INTERNAL RING WELDED TO THE SHELL, REQUIRED FOR A PWHT OF A C.S VERTICAL PRESSURE VESSEL 3/4" SHELL thk, 12'-0" I.D X 16'-0" T/T, two 7/8" ell. heads?
There is a concern about deformation of the shell.
 
Replies continue below

Recommended for you

What does ASME Section VIII, Div 1, Table UCS-56 require?
 
Thanks metengr,
I was not clear.
PWHT is required per service. The question is addressed to the integrity of the equipment during PWHT.
Is it normal to install an internal reinforcement (ring welded to the shell) to avoid deformation of the shell due to PWHT. The PWHT can really affect the shell (roundness, flattening, etc)??
 
The vessel can likely be supported adequately during the PWHT. However, I would make it the responsibility of the organization performing the PWHT to provide that adequate support. I have sometimes seen "spyders" on the insides of vessels. I have also designed additional external saddles for tall slender vessels for additional support.

I don't think that welding on rings is the best solution.
 
Thanks for your help TGS4. I agree.
I just found additional information in other similar thread (2003).
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor