Lion06
Structural
- Nov 17, 2006
- 4,238
I have a question for all – but would especially appreciate responses from structural engineers.
I graduated last may (’06) and have been working for a great company since then. I had an excellent 6-month review and I expect my 1-year review to be at least as good (when it happens in 6 weeks or so). In my short time, I have taken on design tasks that other, more experienced engineers, have wanted off of their desks (for various reasons). Not that any of this was overly difficult, but (I think) shows my willingness to learn and take on more responsibility.
Some of these tasks include designing aluminum structures, masonry shear walls with significant out-of-plane loads, extremely large combined footings, and vibration analysis (and remediation) of an existing wood floor system. All of this is in addition to the more everyday design tasks of retaining walls; steel, concrete, masonry, and wood design, footing design; steel connection design; shop drawing review; review of calculations; etc…
The question I have is how long have others here waited before given project engineer responsibilities? By that I mean being responsible for making most decisions on a project. Right now, I do designs and draw details, then review them with the project engineer (they usually go on the drawings as-is). How long have you been on the job before having those responsibilities yourself?
I graduated last may (’06) and have been working for a great company since then. I had an excellent 6-month review and I expect my 1-year review to be at least as good (when it happens in 6 weeks or so). In my short time, I have taken on design tasks that other, more experienced engineers, have wanted off of their desks (for various reasons). Not that any of this was overly difficult, but (I think) shows my willingness to learn and take on more responsibility.
Some of these tasks include designing aluminum structures, masonry shear walls with significant out-of-plane loads, extremely large combined footings, and vibration analysis (and remediation) of an existing wood floor system. All of this is in addition to the more everyday design tasks of retaining walls; steel, concrete, masonry, and wood design, footing design; steel connection design; shop drawing review; review of calculations; etc…
The question I have is how long have others here waited before given project engineer responsibilities? By that I mean being responsible for making most decisions on a project. Right now, I do designs and draw details, then review them with the project engineer (they usually go on the drawings as-is). How long have you been on the job before having those responsibilities yourself?