v6racer
Electrical
- Sep 30, 2005
- 13
Customer has a building currently fed by a single 2500kva transformer. They planned ahead for load increase and there is a pad for a second 2500kva transformer. These are connected to the dual feed utility on the primary side with S&C switches with the PMH-9 connections, one source transfer and one manual. I know nothing about the internals of a S&C switch. If the transformer are matched 2500kva 5% in parallel doesn't that give me basically a 5000kva unit at 2.5% impedance and my available fault current goes from 59,454 amps to 229,941 amps?