delrob
Mechanical
- Oct 14, 2013
- 3
Can someone tell me if this is in code....im talking of an unbalanced welding technique of bead deposits favoring one side of a weld joint....i had a UNION welder and inspector tells me its not a code violation to do it....its a .270 wall thickness... vertical weld on a fixed panel in a boiler. welder went from root to capping without filling in weld 1st....its also a bad technique to trap slag and have cold lap....but the engineer is also telling me its not in code....as a welder i had to cut out a weld due to this....any info you share would greatly be appreciated