Dear All,
I had started working on a coal fired water tube boiler for power plant. There is a confusion in contract that main boiler is designed on ASME and rest of the parts on GB standard. Following are my queries:
1. What are the boundaries of boiler? Do economizer, super heaters and headers come under boilers?
2. Which joints usually come under PWHT criteria for boiler?
3. As per PW-11 tubes and pipes below 4" RT is not required. So usually boilers have tubes of 2" to 2.5" so we will do zero RT? Also for economizer and super heater piping we will not go for RT?
4. In my area I had observed lot of leakage of boilers in operations especially boiler tubes leakage. Can poor workmanship be a reason or zero RT criteria as per ASME Sec.I? (I know its generic wide scope question if someone could answer)
5. When we are not doing RT for pressure parts what other means are there to ensure joint quality on which we could convince contractor?
I had started working on a coal fired water tube boiler for power plant. There is a confusion in contract that main boiler is designed on ASME and rest of the parts on GB standard. Following are my queries:
1. What are the boundaries of boiler? Do economizer, super heaters and headers come under boilers?
2. Which joints usually come under PWHT criteria for boiler?
3. As per PW-11 tubes and pipes below 4" RT is not required. So usually boilers have tubes of 2" to 2.5" so we will do zero RT? Also for economizer and super heater piping we will not go for RT?
4. In my area I had observed lot of leakage of boilers in operations especially boiler tubes leakage. Can poor workmanship be a reason or zero RT criteria as per ASME Sec.I? (I know its generic wide scope question if someone could answer)
5. When we are not doing RT for pressure parts what other means are there to ensure joint quality on which we could convince contractor?