Hello Respected Members ,
I am trying to run calculation in COMPRESS , for NPS18 Sch120 - SA-106 C smls pipe as cylinder and 2:1Ellip Head 1.25'' Thk SA-516 Gr.70 . Used MDMT is -20deg.F. Design Pressure 2500psi @350degF .
So in result : In Deficiencies report, it gives me that one note : '' for Cylinder Pipe The Rated MDMT of 4.65 deg F is warmer than the design MDMT of -20 deg.F'' & for the Head rated MDMT 0.95 deg F warmer than -20deg.F ''
My request to you , can you please kindly guide me how to remove this deficiencies ? do I need to go with Impact testing check option on it ? Additionally do I need to put full complete vessel for PWHT or just Head and Shell only? I guess as per SecVIII div.1 for SA-516 Gr70 thickness above 1.5'' Normalize is mandatory . but Is it mandatory to put complete vessel as PWHT option on it too?
And after running all different calculation , If I will put / check mark all these 3 option Impact tested , Material Normalize , and PWHT performed , than only I can be able to get report without deficiencies. Do I really need to put all these 3 condition on complete Vessel ?
Thank you .
- AB53Mech.
I am trying to run calculation in COMPRESS , for NPS18 Sch120 - SA-106 C smls pipe as cylinder and 2:1Ellip Head 1.25'' Thk SA-516 Gr.70 . Used MDMT is -20deg.F. Design Pressure 2500psi @350degF .
So in result : In Deficiencies report, it gives me that one note : '' for Cylinder Pipe The Rated MDMT of 4.65 deg F is warmer than the design MDMT of -20 deg.F'' & for the Head rated MDMT 0.95 deg F warmer than -20deg.F ''
My request to you , can you please kindly guide me how to remove this deficiencies ? do I need to go with Impact testing check option on it ? Additionally do I need to put full complete vessel for PWHT or just Head and Shell only? I guess as per SecVIII div.1 for SA-516 Gr70 thickness above 1.5'' Normalize is mandatory . but Is it mandatory to put complete vessel as PWHT option on it too?
And after running all different calculation , If I will put / check mark all these 3 option Impact tested , Material Normalize , and PWHT performed , than only I can be able to get report without deficiencies. Do I really need to put all these 3 condition on complete Vessel ?
Thank you .