dickg
Mechanical
- Jun 24, 2002
- 12
In reference to the Hadlock Dam Failure (Northern NY) they poured RCC until January 17th. The slab was approx 3- 4 feet Thick x 40 feet across the dam and 125 feet long. A picture taken on January 27th showed part of the dam bare and about 70% having 1-3" of snow on it. There was no additional snow of any concequence prior to the resumption of construction on March 23rd when they resumed pouring RCC. The average temperature during that span was 20 degrees f. Overlaying the pre-failure structure with the Clough Harbour failure drawing the initial whirlpool center is nearly in line with the end of the RCC where it transitions to the existing earthen structure. From my calculations the RCC would have contracted approx 3/4" for every 10 degrees of cooling. From what I have read, RCC does not produce a significant amount of hydration heat and with a relatively thin slab and a large amount of surface area it is hard for me to believe that the tempeture of the slab did not drop. Once it contracted any compaction at the juncture with the earthen dam is gone creating a conduit across the entire width of the dam. The only other factor would be the frost in the ground adjacent to the slab at the end. Once they resumed pouring they added insulation over the cold concrete. The Clough Harbour report did not address this issue. I e-mailed the engineer at Clough Harbour questioning this and they acknowleged receipt. They have not commented on this or returned my follow up e-mail. Am I barking up the wrong tree.