gmf
Structural
- Feb 17, 2003
- 25
I am working with a client who has experienced settlements of their building of up to 8"-12". As such, we will be looking to re-level the building by jacking the settled corner back to its original position. The small, wood framed hotel, generates revenue in the summer, during which time the jacking work would be occurring. Would the hotel need to be closed as the building is being leveled?