Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

RE: Rip-rap slopes 1

Status
Not open for further replies.

bmoc

Civil/Environmental
Jul 1, 2003
9
For a marina project, we have boat slips with 8" to 12" rip-rap on the land side (end of slip). Currently, the rip-rap slope is 1:2. Can we make steeper, say 1:1-1/2, or even 1:1?
 
Replies continue below

Recommended for you

It's generally not recommended for loose riprap to go over 2:1
 
Please gentlemen - to reduce confusion put in the H and V. Structural engineers and some civils use V:H and geotechs use H:V. And, many times countries differ as well. Makes things easier-e.g., 2H:1V. Thanks.
 
When I worked for a D.O.T. in a mountainous state we sometimes went as steep as 1.5H:1V. If you ever hiked in the mountains you may see areas where natural piled rocks approach a 1H:1V slope. They are somewhat unstable. If you climb on them, many will roll down hill. It's probably best to stick to 2:1, unless you investigate it further.
 
I would say if you go steeper than 2H:1V, you should plan on hand placement of the stones. If you do hand placement you can go to 1:1 or steeper if the stones are large, but then you are actually building a wall.
 
If you wish to go to a 1:1 slope or steeper there are a ton of other options.
1.)Do you have funds to use other materials?
2.)If so, pour a sea wall and use the riprap as a bank stabilizer.
3.)Use Gabions, You can stack Gabions to what ever slope you desire.
4.)Drive sheet pile.
5.)Where I fish we have used interlocking retaining wall stones.

It depends on what your objective is and how much money you want to throw at it.

Regards,
Namdac
 
bmoc

where are you? It makes a difference.
 
Project is in Bay City, Michigan. I went with 2H:1V MDOT heavy rip-rap slopes. Seawall was too expensive.
 
A good reference for this issue is the Caltrans (State of California) Shore Protection manual that you can download on-line.

Although as many posts have noted, 2:1 has become the standard for ungrouted rip-rap, we have had several projects where environmental agencies have conditioned no grouting, and economics have prevented walls. Select placement of the stones to decrease the voids and create effective point-to point contacts will allow steeper slopes. But a larger skeleton size (i.e larger stones), within intermediate filler sizes will be required, with good field control.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor