Normally We pre manufactured all our rubber lined spools with a supplier, but now is necessary the modification of one in field. Here we have all the tools and good personal to work in that.
In this special case, I am requiring to trim a 1 meter nipple from one spool and this same nipple wil be installed into other. My question is there is a code or standard about the re use of material in this case, where I am reusing a 1meter nipple from practically a new spool to modify another.
Regards,
Normally We pre manufactured all our rubber lined spools with a supplier, but now is necessary the modification of one in field. Here we have all the tools and good personal to work in that.
In this special case, I am requiring to trim a 1 meter nipple from one spool and this same nipple wil be installed into other. My question is there is a code or standard about the re use of material in this case, where I am reusing a 1meter nipple from practically a new spool to modify another.