btv189
Civil/Environmental
- Aug 9, 2013
- 7
I am currently prepping for a base slab that is 2' 9" thick and the drawing calls for #11 on 9" centers, my question is being that the bars have 90 deg bends for tails on the ends of the #11 for all sides of the slab how do you get the first bar that runs perpendicular to be within the tolerances of 117 for the design location of the first bar (as well as the clear distance to the form work)?