Has anyone been involved with recommissioning 260 ton screw type chillers from Trane? If so, what issues did you run into? I am skeptical that it will be as simple as recharge the refrigerant and have a turnkey startup.
The units were originally commissioned in 2000 and mothballed in 2005 when the cleanroom served was put on our central utilities building.
They had operated for 5 years, but were significantly oversized for the load (~60 tons normally, 130 tons design day) and thus had many more starts than normal.
The units were originally commissioned in 2000 and mothballed in 2005 when the cleanroom served was put on our central utilities building.
They had operated for 5 years, but were significantly oversized for the load (~60 tons normally, 130 tons design day) and thus had many more starts than normal.