JD0the0EE
Electrical
- Oct 8, 2009
- 4
I am working on a project to replace a motor control center that burned down. The client wants me to look into re-using the busbars feeding the MCC. The feeder busbars come from a sub-distribution panel nearby and enter through the top of the MCC. It doesn't look like the bars were above the main part of the fire, but I'm sure they got fairly hot. I haven't been able to locate information regarding when or how busbars can be refurbished. Anyone have experience with this?