lslcpfcc
Mechanical
- Jul 20, 2016
- 36
dear,
I calibrated a detector on 10th Feb 2014, with a enclosed tag that addressed the due time is 10th Feb 2015, But after calibration the detector was not used anymore, only stored in the initial box and kept an calibration status. from 6th May 2016, we start to used this detector in working, But now the third part inspector says that the detector has out of calibration because of the due time tag.
the question is, after calibration, the useless time could be counted in the calibration duration, in my opinion, because the detector kept in an calibration status after calibration, so the time from calibration to the initial using day cannot be counted in the calibration duration. the calibration duration start time must be counted from the initial using time.
I calibrated a detector on 10th Feb 2014, with a enclosed tag that addressed the due time is 10th Feb 2015, But after calibration the detector was not used anymore, only stored in the initial box and kept an calibration status. from 6th May 2016, we start to used this detector in working, But now the third part inspector says that the detector has out of calibration because of the due time tag.
the question is, after calibration, the useless time could be counted in the calibration duration, in my opinion, because the detector kept in an calibration status after calibration, so the time from calibration to the initial using day cannot be counted in the calibration duration. the calibration duration start time must be counted from the initial using time.