ChipperB
Civil/Environmental
- Jul 7, 2004
- 33
I need to contruct a concrete vault over an active 30-in PVC C-900 wastewater force main. The flowmeter will be a strap on. My question concerns the pipe/wall penetrations. Because the walls will be poured around the existing force main is it ok for the new concrete to poured dircetly against the pipe or should I make arrangements for there to be some space between the new concrete and the pipe? If a spaace is required, what is a good technique for sealing around the pipe?
thanks
thanks