I am designing a building with reinforced masonry walls (9' high) in a high wind (120+ mph) area. I am coming up with very high reinforcing steel requirements,like a #6 every cell, or a No. 8 every other cell. Could I be missing something, this seems awful high. What are the usual (economical) approaches? TIA