ars001
Structural
- Aug 21, 2006
- 83
I'm designing a foudation for a metal building. I need to provide hairpins at a few column locations. Which is pretty typical. I have a 4" slab and need #6 hairpins. Do I need to follow the ACI limitations for concrete coverage and provide a minimum of 3"(ACI 7.7)or do slab on grades not fall under this provision? Its been awhile since I've done a metal building foundation but it seems to me that I use to put the reinforcing in the center of the slab.