SKIAK
Structural
- Mar 18, 2008
- 145
We designed a concrete utilidor that will be about 6'-0" underground. The walls are 10", the roof has 3" 16ga composite metal deck at 10" full depth with concrete, 8'-0" span, 4000 psi concrete. The contractor has requested that we allow them to pour the slab and a stub of wall in one pour, and the remaining walls and roof in the second pour. We said OK, added some more steel to take the shear instead of a key. The contractor will have formwork for the walls and shoring in the middle. Now the contractor and owner are in a rush to get this done so they have asked how soon the contractor can remove the formwork and shoring, they are hoping for 24 hours. The consensus around the office is "I think its OK, but boy... I'm not sure." I've done a lot of digging around the ACI website and other typical formwork sources and I haven't found anything that would lead me to believe this won't work. It doesn't seem like the low strength will pose any problems, but what you don't know can hurt you. Any bonding issues with this green of concrete? Or anything else?