JoeDirtSoCA
Geotechnical
- Jan 27, 2016
- 11
I'm brand new to this site and kind of new to special inspection. I have a lot of questions!
I was called out to do a special inspection for a CMU retaining wall. The project plans gave the contractor the option to wet set the first course of block into fresh concrete after the footing had been poured,OR they would have to construct a keyway. I was called onsite by the owner to begin inspection after the footing had been poured but before they started to lay up the wall. I immediately noticed that they had not wet set the first course AND there was no keyway. In addition, masonry code and ACI specify that laitance be removed and the footing be cleaned before putting down the first mortar bed. I notified the contractor of this and he seemed perplexed. He didn't know what "laitance" was. The owner called the guy who designed the wall and was told that the contractor needed to grind out a keyway and remove the laitance. After chatting with the contractor as the job progressed I learned that he hadn't done much masonry work in the past (just concrete work) and that this project was a costly learning experience.
On another project I had the same experience with bewildering the contractor when pointing out laitance removal. Is this something that is looked over by other inspectors? Am I being too strict in this regard? Any tips are appreciated. Thanks!
I was called out to do a special inspection for a CMU retaining wall. The project plans gave the contractor the option to wet set the first course of block into fresh concrete after the footing had been poured,OR they would have to construct a keyway. I was called onsite by the owner to begin inspection after the footing had been poured but before they started to lay up the wall. I immediately noticed that they had not wet set the first course AND there was no keyway. In addition, masonry code and ACI specify that laitance be removed and the footing be cleaned before putting down the first mortar bed. I notified the contractor of this and he seemed perplexed. He didn't know what "laitance" was. The owner called the guy who designed the wall and was told that the contractor needed to grind out a keyway and remove the laitance. After chatting with the contractor as the job progressed I learned that he hadn't done much masonry work in the past (just concrete work) and that this project was a costly learning experience.
On another project I had the same experience with bewildering the contractor when pointing out laitance removal. Is this something that is looked over by other inspectors? Am I being too strict in this regard? Any tips are appreciated. Thanks!