When is it generally appropriate to remove shoring from reinforced concrete construction. The case I am specifically asking about is a one-way slab supported by reinforced concrete walls. The 7 day breaks have returned at a little over 3,200 psi of 4,000 psi specified at 28 days.
Is there a rule of thumb to go by?