KAYAKER
Specifier/Regulator
- Feb 25, 2003
- 3
a local contractor poured a monolithic slab radient heat slab over compacted sand(30 x 36)for a private garage. the problem is that the slab is 14" out of square,the building official issued a stop work order untill this is corrected .
the contractor obtained the services of a PE who dictated saw cutting across the slab than drilling holes embedding # 4 bar 10" ( 20db) deep at 1 foot on centers than reforming this new section to be poured -doing so would provide a even exposure along this line in question.
the contractor only drilled in 2 " so as not to damage the pex radient tubing.
another stop work order was issued
the PE has since stated that 2 " of imbeddment is sufficient.
anyone have any thoughts --- is 2 " sufficient?
the contractor obtained the services of a PE who dictated saw cutting across the slab than drilling holes embedding # 4 bar 10" ( 20db) deep at 1 foot on centers than reforming this new section to be poured -doing so would provide a even exposure along this line in question.
the contractor only drilled in 2 " so as not to damage the pex radient tubing.
another stop work order was issued
the PE has since stated that 2 " of imbeddment is sufficient.
anyone have any thoughts --- is 2 " sufficient?