An industrial customer is currently fed via a 2000kVA 13860V delta-600 GrdY 347V. The medium term plan is to replace the 13860V system by a 24940GrdY system, and install a new 2500kVA transformer connected GrdY-GrdY
What would be the drawbacks to remove the present transformer (delta primary) and feed him until then, ie a few years, with a 2000kVA 13860V Y - 600 GrdY 347V. (Note the transformer H0 would be insulated and left floating; only X0 would be connected to the ground grid).
Thanks for your help!
What would be the drawbacks to remove the present transformer (delta primary) and feed him until then, ie a few years, with a 2000kVA 13860V Y - 600 GrdY 347V. (Note the transformer H0 would be insulated and left floating; only X0 would be connected to the ground grid).