Tabaluga
Structural
- Dec 29, 2009
- 27
Hi there,
As per the subject line, I am looking to replace a footbridge deck with a temporary decking system (thinking GRP grating panels?) but struggling to think of sensible options of making connections into the pre-stressed concrete girders as decking is at the bottom of the section so adjacent to the tendons and so need to avoid drilling in that area.
At the moment I was thinking hangers of some sort if they could be anchored in the girder section but above the tendons.
Also a clamping system to the bottom of girders to support tie-rods across - but never come across such a solution on a bridge and so doubt it would be allowed.
Someone has also mentioned chemical or adhesive bonded connections to me, but never seen one for concrete, let alone on a bridge. Not even sure they would be allowed on a footbridge.
Note this is will be a temporary design until they find $ to replace with a new bridge, thus working on the assumption it would need to last say 2yrs max.
Loading is crowd loading 5kN/m2, decking to span 4.5' wide across x 50' long.
Any ideas/suggestions/thoughts much appreciated.
Sketch attached.
As per the subject line, I am looking to replace a footbridge deck with a temporary decking system (thinking GRP grating panels?) but struggling to think of sensible options of making connections into the pre-stressed concrete girders as decking is at the bottom of the section so adjacent to the tendons and so need to avoid drilling in that area.
At the moment I was thinking hangers of some sort if they could be anchored in the girder section but above the tendons.
Also a clamping system to the bottom of girders to support tie-rods across - but never come across such a solution on a bridge and so doubt it would be allowed.
Someone has also mentioned chemical or adhesive bonded connections to me, but never seen one for concrete, let alone on a bridge. Not even sure they would be allowed on a footbridge.
Note this is will be a temporary design until they find $ to replace with a new bridge, thus working on the assumption it would need to last say 2yrs max.
Loading is crowd loading 5kN/m2, decking to span 4.5' wide across x 50' long.
Any ideas/suggestions/thoughts much appreciated.
Sketch attached.