Ben_StructEng
Structural
- Jan 29, 2021
- 9
Hi All,
I've recently migrated from Large commercial Structures to small residential structures and I have come across a few different properties recently where a sub-floor series of Brick piers supporting tiber bearers & Joists above are not founded on a concrete pad footing, but rather just embedded a couple of courses of brickwork onto direct strata.
I am told through word of mouth that this was typical in the 1950's and prior, and that provided you're not trying to add new loads/justify the capacity in anyway that it is still a compliant design due to the 'test of time' theory.
My Questions therefore are:
1. If I am designing for a new load path to these piers and need to assess the pier/foundation capacity, I am needing to do this to new codes, such as AS2870 which requires a min 200-300 deep concrete pad depending on the strata. Due to the fact that the pier was likely compliant back to old standards, am I able to justify the design for new loads based on the bearing applied from the surface area of Brickwork directly to strata? Or do I need to specify a new pad underneath to meet the AS2870 requirements?
2. If I have a scenario where there has been some soil disturbance due to water, or a tree root for example, which is undermining the brick pier due to soil erosion with no concrete pad under, am able to:
- provide a solution to mitigate those issues, and then, provided that there are no new load paths/design items to consider in terms of loading,
- Provide certification that the Pad footing is adequate (Even though it doesn't have a concrete footing in accordance with newer code requirements)
Thanks All. Hope that was clear enough!
Ben
I've recently migrated from Large commercial Structures to small residential structures and I have come across a few different properties recently where a sub-floor series of Brick piers supporting tiber bearers & Joists above are not founded on a concrete pad footing, but rather just embedded a couple of courses of brickwork onto direct strata.
I am told through word of mouth that this was typical in the 1950's and prior, and that provided you're not trying to add new loads/justify the capacity in anyway that it is still a compliant design due to the 'test of time' theory.
My Questions therefore are:
1. If I am designing for a new load path to these piers and need to assess the pier/foundation capacity, I am needing to do this to new codes, such as AS2870 which requires a min 200-300 deep concrete pad depending on the strata. Due to the fact that the pier was likely compliant back to old standards, am I able to justify the design for new loads based on the bearing applied from the surface area of Brickwork directly to strata? Or do I need to specify a new pad underneath to meet the AS2870 requirements?
2. If I have a scenario where there has been some soil disturbance due to water, or a tree root for example, which is undermining the brick pier due to soil erosion with no concrete pad under, am able to:
- provide a solution to mitigate those issues, and then, provided that there are no new load paths/design items to consider in terms of loading,
- Provide certification that the Pad footing is adequate (Even though it doesn't have a concrete footing in accordance with newer code requirements)
Thanks All. Hope that was clear enough!
Ben